Oakton College is continuing campus improvement projects, including those outlined in our recently approved facilities master plan (PDF 7.4 MB), which will result in transformed spaces that create an optimal learning and working environment for students and employees.
Check back often as this page will help minimize operational disruptions and keep you informed of our progress. You can also view areas impacted by construction on our interactive map.
The Latest Updates: Aug. 31, 2026
Space Availability
TenHoeve Center
The TenHoeve conference rooms (1604, 1606, 1608, and 1610) will remain offline through the 2027 calendar year as renovations continue in that space.
However, the TenHoeve classrooms (1603, 1605, and 1607) will remain online for the entire 2026/2027 academic year.
Room 1275 and the Des Plaines Campus store
Starting Sept. 1, room 1275 will go offline, as preparations begin for it to serve as the temporary location of the Campus Store (formerly known as the Bookstore) during renovations to the current Campus Store space.
The Campus Store is expected to become operational in room 1275 toward the end of September.
|
Campus Store, Welcome Center |
|
|
Stakeholders |
Campus Store, Welcome Center |
|
Percent Complete |
3% |
|
Project Start |
Late Fall 2026 |
|
Project Completion |
Early 2027 |
|
The construction contract and the purchase of furniture, fixtures and equipment are expected to be presented for consideration by Oakton’s Board of Trustees at the September board meeting. Pending approval, construction will begin after completion of phase two. |
|
|
Door and Hardware Replacement |
|
|
Percent Complete: |
30% |
|
Project Start: |
4/20/2026 |
|
Project Completion: |
Late 2026 |
|
|
|
|
Office of Student Affairs and Workforce Development |
|
|
Stakeholder(s): |
Office of Student Affairs, Workforce Development |
|
Percent Complete: |
98% |
|
Project Start: |
4/7/2026 |
|
Project Completion: |
8/31/2026 |
|
The contractor is working on rough-in work for mechanical, electrical and plumbing systems. Drywall finishing is nearing completion. Painting is scheduled to begin the week of July 6. |
|
|
Restroom Remodel Project |
|
|
Percent Complete: |
50% |
|
Project Start: |
Fall 2025 |
|
Project Completion: |
Late 2026 |
|
Phase one of restroom renovations are complete and all restrooms at the Des Plaines and Skokie campuses are currently open. |
|
|
TenHoeve Refresh |
|
|
Percent Complete: |
1% |
|
Project Start: |
Summer 2027 |
|
Project Completion: |
Late 2027 |
|
The project is in the design phase. The design team has been holding meetings with stakeholders for planning and design. |
|