Construction Updates

Campus Store and Welcome Center

An image of the Oakton College Leaf on a grey b

Campus Store, Welcome Center 

Stakeholders

Campus Store, Welcome Center 

Percent Complete

 3%

Project Start

Late Fall 2026

Project Completion

Early 2027

The construction contract and the purchase of furniture, fixtures and equipment are expected to be presented for consideration by Oakton’s Board of Trustees at the September board meeting. Pending approval, construction will begin after completion of phase two.

The Des Plaines Campus Store is scheduled to move to its temporary location of Room 1275 in September.

Door and Hardware Replacement

An image of the new door and hardware replacement at Oakton College.

Door and Hardware Replacement

Percent Complete:

30%

Project Start:

4/20/2026

Project Completion:

Late 2026


On-site work has paused on this project. The campus community will be provided with notice prior to the work resuming.

Office Renovations

An image of the Oakton College Leaf on a grey b

Office of Student Affairs and Workforce Development

Stakeholder(s): 

Office of Student Affairs, Workforce Development 

Percent Complete:

 98%

Project Start:

4/7/2026

Project Completion:

8/31/2026

The contractor is working on rough-in work for mechanical, electrical and plumbing systems. Drywall finishing is nearing completion. Painting is scheduled to begin the week of July 6.

Work is substantially complete pending inspections and punch list items. Furniture will be delivered and installed in early September. Moves are expected to occur in September.

Restroom Remodel Project

An image of the Oakton College Leaf on a grey b

Restroom Remodel Project

Percent Complete:

 50%

Project Start:

Fall 2025

Project Completion:

Late 2026

Phase one of restroom renovations are complete and all restrooms at the Des Plaines and Skokie campuses are currently open.

Phase two restroom renovations, including rooms 2214 & 2216 at Des Plaines, are expected to begin in Sept. 2026.

Phase two restroom renovations, including rooms A149, A148, C236, C237 at Skokie, are expected to begin in Sept. 2026.

TenHoeve Refresh

Design phase of TenHoeve Center

TenHoeve Refresh

Percent Complete:

 1%

Project Start:

Summer 2027

Project Completion:

Late 2027

The project is in the design phase. The design team has been holding meetings with stakeholders for planning and design.